(1) Connect a hose to the liquid/gas/high pressure gas pipes and make the vacuum with a vacuum
pump.
(2) The equal oil pipe has gas type of refrigerants. Purge oxygen inside the equal oil pipe.
(3) Compare the external temperature with the temperature below. Keep the vacuum until the
gauge pressure reaches the value in the below table. (For more than 2-and–a-half hours)
Boiling point
of water(℃)
Gauge pressure
mmHg Pa Torr
40 -705 7333 55
30 -724 4800 36
26.7 -735 3333 25
24.4 -738 3066 22
22.2 -740 2668 20
20.6 -742 240 18
17.8 -745 2000 15
15.0 -747 1733 13
11.7 -750 1333 10
7.2 -752 1066 8
0 -755 667 5
Have been achieved in the vacuum drying operation
(4) After making the vacuum, check if the gauge pressure has changed. If no change is found,
then move to the additional refrigerant charging phase.