1. General installation Guide
20
(2) Conveying the outdoor unit
Process photo Work details
Things to obey
(installer)
Checking the
outdoor unit.
A group of four move the
outdoor unit(22HP)
Check for damages in the
outdoor unit.
(3) Mounting the vibration-proof board
Process photo Work details
Things to obey
(installer)
Mounting the
vibration-proof
board.
Install it in the upper area.
- Do not change the
location of the vibration-
proof board.
- Check the location in the
diagram once again.
(4) Connecting the vibration-proof board
Process photo Work details
Things to obey
(installer)
Connect the
outdoor unit to
the vibration-
proof board.
Bolting of the vibration-
proof board.
Check bolt installation and
the final levelness.
(5) Completed installation of outdoor units
Process photo Work details
Things to obey
(installer)
Completed
installation
Reinforce the outdoor
unit.
Check for reinforcement.